Frequency of time overrun causes in road construction in Palestine: Contractors’ ViewReportar como inadecuado




Frequency of time overrun causes in road construction in Palestine: Contractors’ View - Descarga este documento en PDF. Documentación en PDF para descargar gratis. Disponible también para leer online.

Organization, technology & management in construction : an international journal, Vol.5 No.1 July 2013. -

Time, cost and quality have their proven importance as the

prime measures for project success. However, the history of

the construction industry worldwide is full of projects that were

completed with significant time and cost overruns. This study is

conducted to investigate the occurrence frequency of time overrun causes in road construction projects in the West Bank in

Palestine from contractors’ viewpoint through a questionnaire

survey. The field survey included 34 contractors. 52 factors

affecting time overrun were identified during the research. The

survey concluded that the top ten frequent factors are: segmentation of the West Bank and limited movement between areas,

political situation, progress payments delay by owner, lack of

equipment efficiency, difficulties in financing project by contractor, personal conflicts among labors, poor communication

by consultant with other construction parties, conflict between

contractor and other parties, award project to lowest bid price,

unreasonable project time frame by the owner.

Delay; Time overrun; Frequency; Road Construction; Contractors; Palestine



Autor: Ibrahim Mahamid -

Fuente: http://hrcak.srce.hr/



DESCARGAR PDF