Automated Planning and Scheduling for Industrial Construction ProcessesReportar como inadecuado




Automated Planning and Scheduling for Industrial Construction Processes - Descarga este documento en PDF. Documentación en PDF para descargar gratis. Disponible también para leer online.

Dynamic Programming, Domain Independent Artificial Intelligence Planning, Time Stepped Simulation-based Scheduling, Automated Planning and Scheduling, Pipe Spool Fabrication Sequence, Industrial Construction, Module Installation Sequence

Hu, Di

Supervisor and department: Dr. Yasser Mohamed Civil and Environmental Engineering

Examining committee member and department: Dr. Tarek Hegazy Civil and Environmental Engineering, University of Waterloo Dr. Amit Kumar Mechanical Engineering Dr. Simaan AbouRizk Civil and Environmental Engineering Dr. Aminah Robinson Fayek Civil and Environmental Engineering Dr. Amy Kim Civil and Environmental Engineering

Department: Department of Civil and Environmental Engineering

Specialization: Construction Engineering and Management

Date accepted: 2013-03-19T10:35:37Z

Graduation date: 2013-06

Degree: Doctor of Philosophy

Degree level: Doctoral

Abstract: Cost overrun and schedule slippage are common problems for mega industrial construction projects. Lack of effective planning and scheduling tools is identified as a major contributing factor to poor project performance. Planning and scheduling tools should be custom designed to address the characteristics of mage industrial projects: unique components, modularized execution strategy and its extremely accelerated project delivery. The main objective of this research is to investigate and develop automated solutions for planning and scheduling two essential stages of mega industrial projects, shop fabrication and on-site construction. This research explores use of discrete event simulation DES to automate scheduling of shop fabrication and on-site construction processes. For industrial fabrication shops, a new simulation structuring methodology is developed to address the complex routing issue. Following this methodology, a simulation model is developed for pipe spool fabrication shops, which performs scheduling for shop operations, and mainly evaluates the impact of fabrication sequence on the spool cycle time. For site construction, a time-stepped simulation framework is developed to address congestion and dynamic resource allocation issue. For a real-life industrial construction case, this framework returns a schedule that has 12% shorter duration than those generated from Microsoft Project and Primavera P6. The research investigates use of domain-independent Artificial Intelligence AI planning to automate the sequence planing for pipe spool fabrication and on-site module installation. Experiment results show that AI planning is not suitable for sequencing spool fabrication due to the limited parsing capability of existing AI planners. However, AI planning is efficient to identify feasible sequence plans for module installation based on the current module availability and installation status. The research finds Dynamic Programming DP is suitable to sequence pipe spool fabrication. A DP algorithm is developed to automatically identify the optimal sequence in terms of the minimum position welds. Simulation experiments were conducted with 29 real-life spools to quantify the performance improvement obtained from the DP algorithm. Results showes that by using the DP algorithm, there is a 45% reduction in the number of position welds, which is translated to a reduction in the total cycle time, ranging from 4.8% to 12%.

Language: English

DOI: doi:10.7939-R3V88D

Rights: Permission is hereby granted to the University of Alberta Libraries to reproduce single copies of this thesis and to lend or sell such copies for private, scholarly or scientific research purposes only. Where the thesis is converted to, or otherwise made available in digital form, the University of Alberta will advise potential users of the thesis of these terms. The author reserves all other publication and other rights in association with the copyright in the thesis and, except as herein before provided, neither the thesis nor any substantial portion thereof may be printed or otherwise reproduced in any material form whatsoever without the author's prior written permission.